A.47 Natural Gas Compressor Station, MS
A.47.1 Summary
|
Environment: |
Freshwater |
|
Scale: |
Full |
|
Contaminants of Concern: |
PCBs |
|
Final Remedy: |
Creek flow diverted by pumping to nearby tributary to allow for dry excavation. Little to no dewatering of excavated material done. Typically dry enough to put into vehicles to transport to Emelle, AL.
In a few instances, fly ash or lime was mixed in to make the material dry enough for transport. |
A.47.2 Site Description
Year: 1997
Contaminated sediment area: 2 mile stretch on the Little Conehoma Creek approximately, 15-25 ft wide.
Water Depth: Creek bed/flood plains
Target Volume:
51,432 yd3 of stream sediment
8,290 yd3 of floodplain soils.
Actual Volume Removed: 23,883 yd3 excavated
A.47.3 Remedial Objectives
1ppm PCB for Creek, 5ppm > for floodplain soils.
Sediment thickness: At one point, excavation to depths of 8-10 ft necessary to reach cleanup levels. Remainder were 0-8 ft.
Dredge depth: Avg. 1 ft, more near outfall.
A.47.4 Remedial Approach
Dry excavation (Caterpillar 320 and long stick excavator)
A.47.5 Monitoring
There were no suspension controls because dry excavation was used. Air monitoring was in effect.
All remediated areas were at or below 1 ppm. All goals were met.
A minimum of 2 ft of clean backfill was installed along the banks of section 26. Backfill was followed by seeding and application of mulch.
A.47.6 References
Major Contaminated Sediment Sites Database; Sept. 2004 as updated 2008. http://www.smwg.org/MCSS_Database/MCSS_Database_Docs.html.
Publication Date: August 2014